Post by johnnypc on Feb 15, 2017 13:08:52 GMT -5
?
|
|
friar82
Administrator
BCC Member
Posts: 8,153
|
Post by friar82 on Feb 15, 2017 13:16:59 GMT -5
Just recently, I read something that had me thinking that all of the site work is complete. Wondering the same about more visible, above ground work.
|
|
thefriarman
Administrator
Global Moderator
Posts: 5,792
|
Post by thefriarman on Feb 15, 2017 13:18:44 GMT -5
Last I heard they were doing all the infrastructure work including knocking down houses they had bought although I also heard one guy was holding out on selling his house.
I don't think they've started any structure building yet at least does not look that way when I go by the area on the way to hockey games.
|
|
|
Post by wtm97 on Feb 15, 2017 14:00:19 GMT -5
Think Driscoll said on Cooley's radio show that it would take a year once actually started...(sounds aggressive)
|
|
pcdad
Friar Fanatic
Posts: 3,707
|
Post by pcdad on Feb 15, 2017 14:08:23 GMT -5
They built the Empire State Building in less than a year.
They built the original Yankee Stadium in less than a year.
But Providence contractors didn't build them.
|
|
|
Post by bostonfriar on Feb 15, 2017 15:07:21 GMT -5
The one holdout has been at issue for several years. PC moved on from dealing with the owner a few years ago. That house is not holding up the project. Quite a few other homes have been purchased and demoed plus the street purchase provides additional land.
The start of worked moved from summer 2017 to 2018, as I hear it because the cost estimates were higher than the funds budget so value engineering work is underway to get back to cost targets.
In general PC building projects begin in the Spring and tale 18 minths.
|
|
friar82
Administrator
BCC Member
Posts: 8,153
|
Post by friar82 on Feb 15, 2017 15:37:33 GMT -5
So we should set our sights on a Fall of 2018 opening...
|
|
|
Post by drairf on Feb 15, 2017 16:23:21 GMT -5
What is the address of the one hold out? Is he/she going to have a house surrounded by campus buildings?
|
|
|
Post by dmac80 on Mar 2, 2017 13:09:14 GMT -5
|
|
|
Post by bostonfriar on Mar 2, 2017 15:48:15 GMT -5
2019 What is the address of the one hold out? Is he/she going to have a house surrounded by campus buildings?
|
|
|
Post by drairf on Mar 2, 2017 16:35:33 GMT -5
2019 what?
|
|
|
Post by bostonfriar on Mar 2, 2017 21:27:22 GMT -5
82 said Ruane would open in 2018. 2019 is most likely
|
|
|
Post by 5thirty on Mar 3, 2017 7:12:39 GMT -5
This is beyond the college arms race. This is Roman Empire stuff.
|
|
friar82
Administrator
BCC Member
Posts: 8,153
|
Post by friar82 on Jun 15, 2017 17:05:10 GMT -5
Update:
|
|
|
Post by wtm97 on Jun 30, 2017 8:58:23 GMT -5
Already having completed both recent new buildings on campus "on time and on budget" gave the chosen outfit a leg up on winning the bid. Let's get those shovels in the ground and get this built...BRICK BY BRICK. Is it true that Dex is donning the hard hat as. Consultant?
|
|